TARGET
DISTRIBUTION CENTER
Langan provided comprehensive site/civil
design services for a 1.3 million square foot warehouse distribution
center for this 130 acre site located along Interstate 81 near
Chambersburg in central Pennsylvania. Langan designed and permitted
all site improvements including detention basin design for over
150 acres of on-site and off-site development. Langan also designed
and coordinated sanitary and water distribution systems for the
regional center, and engineered a 3,000 linear foot roadway along
the sites frontage. Elements of our work included a fire
water storage tank design, sanitary sewer planning through the
Township and PADEP, and utility coordination. Challenging constraints
to the design and construction included the presence of existing
twin regional high pressure gas mains along the sites border,
and the concurrent construction of a new high pressure gas main.
Detailed coordination in the roadway design, earthwork activities
and blasting work were performed with multiple public and private
agencies. Overall earthwork volumes in excess of one million cubic
yards, and an estimated rock cut in excess of 700,000 cubic yards
required a detailed geotechnical engineering study and preparation
of site work specifications used by the contractor. Engineering
inspection and oversight was provided during the geotechnical
site investigation, and during earthwork and construction of the
center.