Manzanillo International Terminal
OVERVIEW
The new construction required dredging of the adjacent bay for ship movements. In addition, a new 16-hectare container storage area was created within the existing bay. Deep foundation support of this area was not economically feasible. Consequently, a vertical wick drain system combined with fill surcharging was used to accelerate settlements to allow for near future construction while minimizing post-construction settlements.